| Owner: GTAA |
Client: Dufferin |
| Value: |
Schedule: 3 Months |
| Percentage Recycled: 100% |
|
Description: As previously used access roads became redundant with the closure of the old Terminal 2, demolition of four bridges was required. During the three month period:
- Each of the four bridge decks were demolished and removed individually throughout separate 24 hour periods.
- Abutments, footings and foundations were removed from each bridge and hauled off site.
- All concrete recycling was completed on site.