Description: As previously used access roads became redundant with the closure of the old Terminal 2, demolition of four bridges was required. During the three month period:
Each of the four bridge decks were demolished and removed individually throughout separate 24 hour periods.
Abutments, footings and foundations were removed from each bridge and hauled off site.