A Force To Be
Wrecking
with
Elgin Mills Bridge
Owner:
York Region
Client:
Dufferin
Value:
$150,000
Schedule:
2 Weeks
Percentage Recycled:
100%
Description:
Along Highway 404, demolition of the Elgin Mills Bridge was required. Within a two week period:
The bridge deck was demolished over a 10 hour span and prepared for recycling.
All footings and foundations were completely detached and recycled on site to be removed.
All material was hauled off site.